Measure L Construction Update 11.11.2026

Progress Worth Celebrating at Bonny Doon Elementary

Exciting progress is taking shape at Bonny Doon Elementary School as our Measure L campus improvements continue.

A Milestone Worth Celebrating

We're happy to share that the main entrances to the school office and Multipurpose Room (MPR) are officially back open. The new concrete walkway fully cured and ready for use.

And what better way to celebrate than together? Last week, our school community gathered on the newly completed concrete area for a Friendsgiving concert and potluck. It was wonderful to see families, students and staff enjoying this improved space and sharing in the excitement of our campus transformation.

What's Happening Next

Construction continues in several areas of campus, with upcoming work focused on:

  • Classroom Improvements: Wrapping up painting and moving forward with flooring, doors and finishing touches in classrooms. Prior to Thanksgiving Recess, our 2nd through 6th grade classrooms will be moving into the newly completed classrooms. Stay tuned for a request for volunteer help.
  • Restroom Modernization: Continuing flooring, partitions, fixtures and other improvements to student restrooms.
  • Campus Accessibility and Site Work: Continuing grading, sidewalk improvements and work on the lower campus ramp. We expect the ramp connecting upper and lower campus to open as soon as next week, allowing our field project to begin.
  • Safety and Infrastructure: Advancing fire alarm upgrades and preparing the site for generator installation.

A Few Important Reminders

While we're excited to re-open key campus pathways, construction remains active in other areas. Families and staff should continue following posted signage, using designated pedestrian routes and allowing extra time when navigating campus.

Looking Ahead

Over the coming weeks, we anticipate continued progress on classroom and restroom improvements, with additional finishing work, inspections and testing scheduled as construction moves forward.

Every completed improvement brings us closer to a safer, more accessible and modernized campus for our students and staff. Thank you to our Bonny Doon community for your continued patience and flexibility.